wildcat
Big Sandy ISD
journey

Construction Photo Gallery

Science Lab Expansion
 

Updates as of January 15, 2010 - hey started around 11:00 am on Monday on the front of the school with a block wall that ran from JH to the auditorium on the inside of the building. Tuesday and Wednesday the crew moved to the back of the school and finished the brick work on the science lab and continued laying split face block and brick on the elementary addition.   
 

Updates as of December 11, 2009 -This past week was mostly mason and A/C work on the construction. The A/C contractor completed installing the duct work in the science labs and installed new curbs on the roof for the A/C units to sit on and installed the units. Masonry is completed in the science area and the steel erectors are scheduled to be here next Wednesday to start installing the roof joist and decking on the Elementary addition and the science room.
 

Updates as of December 4, 2009 - This week construction crews started installing duct work to prepare for Ac units for science labs. The electricians and plumbers have worked all week they have completed the water lines and started connecting the gas connections.  The electricians have also been pulling wire.  The masonry crews have completed the block work at science labs.

Roofing crews will be here Monday to install roof joist and decking.
 

Updates as of November 13, 2009 - Plumbers and electricians were able to button up some lose ends. Plumbers connected water pipe and gas lines while electricians ran conduit for lighting. 
 

Updates as of November 6, 2009 - Plumbers, electricians and masons were able to work in there all week. The old electrical panels were removed and the mezzanine was totally rebuilt for the mechanical room. The main interior block wall is almost complete.
 

Updates as of October 31, 2009 - Plumbers have installed vent piping and have started on running the over head water lines. The electricians have started installing electrical conduits for the lighting and staying ahead of the masons as they lay block in the interior of the science labs. As of Friday the 30th four interior door frames are in place as the masonry crews put up the walls. Crews have cut out the wall were the exterior door of the science lab will be installed.
 

Updates as of October 23, 2009 - This week the steel crew was able to install the red iron in the science labs and completed the job two days ahead of the schedule which allowed the support scaffolding to be removed. Now it is ready for the masons to start their work inside. This is good news, because even if it rains the masons will be able to work inside laying block with the plumbers and electricians.
 

Updates as of October 16, 2009 -The construction at the school has been hampered by all the rain the past two weeks. Numerous attempts were made to make some progress.
 

Updates as of September 11, 2009 - The rough plumbing in the old Ag shop should be completed this week. Approximately half of the gas lines have been tested and backfilling the ditches are almost complete. Electricians started Friday.
 

Updates as of September 18, 2009 - Contractors were not able to work outside this week due to rain. In the old Ag shop (new science labs) the concrete was poured back into the trenches. The trenches had been dug in that area to lay the pipe for plumbing and electrical conduits.
 

Updates as of September 4, 2009 - Construction in the old Ag area is progressing with gas lines and drain pipes in. Electricians will start Tuesday, September 8 on electrical conduits.
 

Science Lab Expansion updates as of August 28, 2009 - The old Ag shop and the two attached classrooms have been gutted this summer in preparation for the new science labs and classroom. Sub floor work is taking place to install plumbing for the labs. 

 
 
 
 
 

calendar

super's note

Counselor's Corner

401 Wildcat Drive  ●  Big Sandy, TX 75755   ●  Phone (903) 636-5287  ●  Fax (903) 636-5111

© 2009 Big Sandy Independent School District