Updates as of
December 11, 2009 - If you have driven by the front of the
school this week you would have noticed that the walls have started
up in front. Freezing weather had slowed down the masonry crew this
week.
Updates as of
November 6, 2009 - This week was a good week for
construction. Concrete crews were able to pour a little over 170
yards of concrete Thursday morning for the JH and HS addictions.
They started at 4:00 am and had all the concrete out by 7:00 am.
Then they spent the rest of the day finishing and removing form
boards.
Updates as of
October 31, 2009 -
Once again this week the weather (rain) hasn’t allowed any outside
construction. Hopefully next week with be better.
The concrete crews came on Friday and started trying to dry out the
front and hopefully will get to pour concrete next week.
Updates as of
October 23, 2009 - The concrete crew
moved to the front of the school and started preparing the sight for
concrete. The plumber finished installing the under ground plumbing.
The site is too wet from this week’s rain and concrete crew is
working hard to dry it. Hopefully they can schedule concrete for
this coming week.
Updates
as of October 16, 2009
-The
construction at the school has been hampered by all the rain the
past two weeks. Numerous attempts were made to make some progress.
Updates
as of October 2, 2009 - Temporary drain pipe was put in place to keep roof water off the
construction site at the front of the school.
Updates
as of September 25, 2009 -
Friday the concrete crews poured the foundation in front of the
school. The masons are scheduled to come in Monday, September 28 to
lay block for foundations.
Updates
as of September 18, 2009 -
Contractors were not able to work outside this week due to rain.
Updates
as of September 4, 2009 - Dirt work is completed in front of the
school. Dirt has been removed and select fill was brought in for the
foundation. Friday, the concrete crews were here to install batter
boards and mark the area for the concrete foundation work.
Front
Parking
Expansion
updates as of August 28, 2009 -
The parking lot in front of
the junior high and high school has been removed. Dirt work will begin
shortly in preparation for the secure entrances and classrooms that will
be on that site.