Updates
as of September 11, 2009 -
The auditorium carpeting was in the process of installation this
week. It has taken a little longer then anticipated. The carpeting
should be near completion by Monday, September 14.
Updates
as of September 4, 2009 - Seating for the auditorium arrived
Monday, August 31. Anchor holes were laid out and drilled on Tuesday
and installation of the seats started Wednesday. The contractors
finished installing the chairs Friday at noon. The auditorium is
looking very nice. The carpet in the walkways is scheduled for
installation the week of September 7.
Auditorium
updates as of August 28, 2009 - The seats were removed, flooring
taken up and ceiling scraped in preparation for painting, new
flooring, lighting, sound boards and new seating. The painting is
finished and new lighting and sound boards are installed. The new
seating is scheduled to arrive on Monday, Aug 31 and installation
will take most of that week. After the seating is installed the
final step will be the carpeting. The auditorium should be ready for
use by mid-September.